American Rescue Plan Act (ARPA)

The federal American Rescue Plan Act (ARPA) allocated $1.9 trillion to COVID-19 relief and economic recovery. The City of Chester received $30 million, which it obligated towards the array of projects listed below.

ARPA Project Statuses

Total ARPA Budget

$30,357,628

ARPA Actuals to Date

$22,136,427

ARPA Funds Remaining

$8,221,201

Completed ARPA Projects

Project NameFinal BudgetFinal Actuals
Revenue Replacement - Operations$10,000,000$10,000,000
Engineering & Asset Management Capital Planning Service Proposal from HRG$171,000$171,000
Ventilation Improvements - City Hall$97,266$97,266
Fire Station 82 - HVAC$33,600$33,600
City Hall A/V Upgrades for Council$32,207$32,207
Equipment - Dell Computers$177,549$177,549
Software/Licenses - Edmunds$150,000$150,000
Vehicles$475,610$475,610
Vehicles - Fire$117,627$117,627
Quick Response Service Certification and Software$33,066$33,066
Vehicles - Streets and Highways$200,350$200,350
Reaney Street$145,624$145,624
Pool/Memorial Park Bathroom/Safety Upgrades$326,830$326,830
50 gal. Waste Trash Bin$567,902$567,902
Hazard Pay$315,121$315,121
City Hall HVAC$701,753$701,753
Fire Station 81 & 82 Repairs - COMPLETED$154,536$154,536
Chester Park Garage Improvements - FUNDED via CEDA$-$-
Temporary Staffing Firm$131,331$131,331
Blight Assessment/Cyclomedia Imagery$94,113$94,113
Parking Study$49,255$49,255
City Hall Renovations & Roof Repairs$936,998$946,304
Engineering Firm$108,287$108,287
Street Signage$88,692$88,692
All Completed Projects Total$15,108,717$15,118,023

In Progress ARPA Projects

Project NameFinal BudgetActuals to DateRemaining Funds
Codification Services$29,995$20,997$8,999
UHY Advisors$225,200$173,108$52,093
Playground Improvements & Park Safety Upgrades$323,750$76,874$246,876
Network Upgrade & Office 365 & IT UPS$896,951$790,395$106,556
Homeowner / Landlord Improvement Program$1,000,000$654,370$345,630
City Staff - RTW Positions, Sr. Accountant,$2,419,826$2,305,066$114,760
Chester Clean Ways$76,886$28,813$48,073
Police Station Repairs (Evidence Room)$500,000$21,060$478,940
Business Façade Improv. Program (FIP)$253,265$55,338$197,927
Public Works Garage & Shed Repairs$8,083,038$2,892,384$5,190,653
Purchase Fire Truck (Ladder Engine) - MOU Obligated$1,440,000$-$1,440,000
In Progress (on track) Sub-total$15,248,911$7,018,404$8,230,506

New Public Works Facility

Memorial Park Pool Upgrades

Reaney Street Improvements